Over
$12 Million of construction has been completed on the site being new
kiln slabs, debarker foundations, boiler and heat plant foundations,
saw dust bunkers, underground tunnels, and a very large remanufacturing
building.
Designed by Stiffe Hooker Ltd this work was completed over a period
up to April 2007.
The client demanded a very high standard of finish to the structural
steel framed building and precast panel work requiring high levels of
supervision of all the subtrades involved.
The remanufacturing building has a large free span structure with a post-tensioned floor slab to eliminate construction and shrinkage joints.
|