McMillan & Lockwood

Mount Maunganui Fire Station

Completed in 2006 this two storey building houses a new station for 4 appliances and support area for permanent shift crews of 5 staff. Designed by MSM Architects and valued at $2.1 Million this contract won a gold medal at the RMBA Commerical Awards in 2007.

Constructed with a structual steel and timber framing the building has various exterior cladding options including weatherboards and Hinuera stone facings.

Address:
2-4 Golf Road Mount Maunganui
Cost:
$2.1 Million
Client:
NZ Fire Service
Build Time:
11 Months
Completed:
October 2006
Contract Type:
NZS:3910
 
Architect:
MSM Architects
Structural:
G A Hugh & Associates
Mechanical:
All Seasons
Electrical:
Electrical Consulting Services Ltd
Data / Com:
Steelcom Electronics
Fire:
Entire Fire
Key Subcontractors:
Higgins Group
   
Project Manager:
Alan Benjamin
Site Manager:
Done Quarrie
Quantity Surveyor:
Stephen Hope